Moving LOINC to monthly releases
Live readout of the process design for monthly cadence — the pipeline model, the working vocabulary, and what's actually decided vs. still open.
Three release states, running at once
Every month, multiple releases exist simultaneously, each in a different state. Only Authoring can span more than one release at a time.
Release
Being published — the technical work of assembly and going out the door (FHIR build, ETL, handoff to West Coast Informatics).
Validation
Artifacts being checked. Whole-release level, one release per month — not term-level QA.
Authoring
Active editorial work. Can span several future releases at once — not serial. This is what absorbs long-lead-time content (CMS, Gravity, large surveys).
| Month | Releasing | Validating | Authoring |
|---|---|---|---|
| This month | 2.84 | 2.85 | 2.86, 2.87, 2.88 |
| Next month | 2.85 | 2.86 | 2.87, 2.88, 2.89 (new) |
| Month after | 2.86 | 2.87 | 2.88, 2.89, 2.90 |
When a release's content-freeze date arrives: if the targeted content is done, it moves to validation. If not, it gets pushed to a later release rather than holding everything up in place.
The working vocabulary
Steven: “These are the words we're going to use today.” Replaces looser prior usage (e.g. "QA" / "post-QA review").
| Term | Definition |
|---|---|
| Release | The continuous offering-through-QA lifecycle for a set of terms. Several releases can be open at once. |
| Authoring | Batch editorial work targeted at one specific release. Can span multiple months in parallel. |
| Content freeze | A date, not a window — when authoring stops for a given release and it moves to validation. |
| Validation | Checking of release artifacts, whole-release level (one release, one month) — not term-level QA. |
| Release month | The month the technical assembly/publishing work happens. |
| Task | A unit of editorial work assigned to a person, targeted at a release. |
| Workspace | A sandbox attached to a task — edits land here first. |
| Cutover | Moving work from workspace into QA to close the release — an end-of-month action. |
| QA review | Replaces the old term "QA." |
| Secondary QA review | Replaces "post-QA review." Optional, not strictly hierarchical.Criteria for when it's required vs. optional — deferred, not yet defined. |
Week by week
Validation spans a full month (vs. today's ~2 weeks) because authoring and publication for other releases run in parallel the whole time.
| Week | Focus |
|---|---|
| Week 1 | Buffer to absorb any overrun from the prior release. Validation opens, assignments given out. Deliberately kept light. |
| Week 2 | Core validation work — environment, artifacts, etc. |
| Week 3 | Continued validation workflow — issues logged and addressed, closing out and signing off by end of week. |
| Week 4 | Freeze, publish, out the door. Handoff to West Coast Informatics (FHIR build), ETL to servers. |
Urgent/critical late items: no dedicated lane in the model, but intended to have enough slack to absorb genuinely critical content unless a release is truly at the door. Decision: keep the existing "special use" tag mechanism specifically so urgent items don't have to break cadence.
The 15th of every month
Chosen as a fixed calendar date (like RxNorm), not an "Nth weekday" rule — the room valued predictability over dodging occasional weekend-adjacency.
| Month | Treatment |
|---|---|
| December | Fully skipped. |
| July | Deliberately reduced scope around the 4th — not a full skip. |
| October / November | Earlier leaning was "shrink, don't skip" (conference in October; Thanksgiving in November; avoid two consecutive full skips) — not re-confirmed after the 15th-day decision. See Open items. |
Right-sizing habit (new): when planning a month's authoring work, explicitly check which release month it lands in and size accordingly (e.g. "we're authoring 2.87 now, its release falls in October — that affects what goes in it").
Release operating cadence
A three-tier meeting structure so status isn't found by asking people one at a time. Each tier does exactly one job.
| Tier | When | Length | Who | Output |
|---|---|---|---|---|
| Release planning | Once/cycle, at scoping | 60–90 min | Contributors + stakeholders | Committed work plan, named owners, dates |
| Standup | Tue / Wed / Thu | 20 min | Full team | Blockers routed with an owner |
| Working session | Same/next day, as needed | 30–45 min | Only those involved | A decision, an owner, a date |
Core principle: the standup detects and routes blockers — it does not solve them. Problem-solving happens in the working session. And: the standup can only report against what planning committed; without planning, standup degrades into a status call.
| Commitment | What that means |
|---|---|
| Scope | Itemized per release, not described in aggregate |
| Owners | A named person per item — never a team |
| Dates | A target date per item, not just the release cutoff |
| Dependencies | Identified and sequenced between items |
| Risks | Known risks, each with an owning person |
| Segment | ~Time | Covers |
|---|---|---|
| Per release | ~4 min | Terms passed/failed validation since last standup + top failure reason; at-risk-against-cutoff yes/no; blockers (what, who, needs which people) |
| Intake | ~4 min | Arrived since last standup; oldest open item age; count past target |
| Routing | ~4 min | Anything escalating — every blocker leaves with an owner and a working-session slot |
Rule of thumb: if an answer would take longer than one sentence, it goes to the parking lot instead of eating standup time.
| Today | Under this cadence |
|---|---|
| Status found by asking individuals | Reported in a standing 20-minute slot |
| Scope committed informally, ownership implicit | Committed at planning, named owner per item |
| Intake worked when someone notices it | Reviewed three times a week |
| Blockers raised in 1:1s or not at all | Routed to a working session with a date |
Explicitly out of scope for this framework: governance, metrics, and the QA-gate conversation. Status: presented in Steven's deck; not yet confirmed as adopted in live discussion as of this update.
What's actually settled
| Decision / action | Owner | Due | Status |
|---|---|---|---|
| Keep the "special use" tag for urgent/critical items so they don't break monthly cadence. | — | Effective now | Decided |
| Critically scrub the wiki guidance and validation processes — what works, what doesn't, what needs updating.Joe has an AI-condensed SOP-repo draft as a starting point, distinguishing the "human side" (SOPs) from the "system side" (automated validation rules). | Joe (+ Steven) | Not firm — first pass before next release | In progress |
| Drop full community announcements per release — just technical release notes + a plain notification. Save bigger announcements for genuinely significant changes (pre/post-coordination, new domain model, file-format changes). | — | Effective now | Decided |
| Keep 3 community touchpoints/year: 2 virtual webinars + 1 in-person, timed to the October conference and recorded. | — | Effective now | Decided |
| Open validation (file/package-level checks, not term QA) to non-terminologist volunteers — no terminology background required, just clear instructions. | Blake + volunteers | Ongoing | Decided |
| Capacity planning practice: commit under perceived capacity, not a wish list — leaves buffer for urgents; unused buffer just means extra gets pulled forward.Validated live via a trial exercise for the Jan/Feb release cycle. Planned time off factors into capacity. | Whole team | Effective now | Decided |
Risks
| Risk | Detail | Status |
|---|---|---|
| West Coast Informatics (WCI) integration time | WCI's FHIR pipeline needs a full fresh export/re-ingest every single release, not incremental. Their first real run (turned on the day of this meeting) reportedly took several days. Clarified live: this build work happens after release lock, not before — WCI gets the full following month (15th to 15th) to build from a locked release, not a tight post-release window. | Mostly resolved |
| Redundancy / bottleneck on single-owner content areas | Elizabeth holds essentially all survey work with no backup — a real risk to authoring continuity if she's out. Precedent: a prior attempt to cross-train someone else (Felicia) onto CMS content was contractually forbidden by that work's funding contract. Not a training gap — a funding/contracting constraint ("our hands are tied"). | Unresolved |
Bonus insight from the WCI discussion: monthly cadence generally lowers the cost of late-breaking items — instead of an in-place fix/revalidation scramble, a late item just waits for next month's release (“you got 28 days, you can wait”).
Open / unresolved
| Item |
|---|
| Criteria for when secondary QA review is required vs. optional — explicitly deferred. |
| Whether a rotating validation-focus cycle (e.g. "this month, extra scrutiny on panels") is feasible instead of full review every release — raised, not resolved; may not meet quality bar. |
| Trial/dry-run monthly release cycles before real cutover — floated (loosely around a "February" reference point), timing and logistics not finalized. |
| October/November skip-vs-shrink treatment — not re-confirmed after the release-day decision landed on the 15th. |
| How to publicly frame WCI's role/authority in community communications — marketing wants "agent" framing, Steven is holding off in favor of a low-key technical notification. |
| Server/staging budget and decoupling the ServiceLink API to the cloud — wanted, no owner or date yet. |
Sources
Live transcript of the HDS Team F2F, Aug 27, 2026, captured via Zoom, continuing directly from the 2.83 release post-mortem. Full discussion detail is kept in loinc-processes/ReleaseTasks/loinc-monthly-release-planning/monthly-release-notes.md.