The end-to-end monthly release workflow
Live readout building on Day 1's pipeline model — task/workspace mechanics, tooling, and handoffs for running monthly releases in practice.
Open items going into today
These were left unresolved at the end of the Aug 27 session on the pipeline model and cadence.
| Item |
|---|
| Criteria for when secondary QA review is required vs. optional. |
| Whether a rotating validation-focus cycle is feasible instead of full review every release. |
| Timing/logistics of trial monthly release cycles before real cutover. |
| Ownership and firm date for the wiki/SOP scrub. |
| Final skip/shrink treatment of October and November. |
| How to publicly frame WCI's role/authority in community communications. |
| Server/staging budget and ServiceLink API decoupling. |
What's actually settled
Nothing logged yet — this fills in as the meeting runs.
| Decision / action | Owner | Due | Status |
|---|---|---|---|
| New LMS tooling for monthly releases — new Tasks / My Tasks / Release Management nav, a workspace indicator ("no workspace set" / "set workspace"), plus general UI polish (condensed grids/forms, fixed column-squish on split view, subgrids collapsed by default with height caps). Dev-side, being demoed live.Dev-environment link to be shared with the team shortly. | Steven (dev) | Ongoing | In progress |
Conflict detection across concurrent releases
The mechanism that makes Day 1's "multiple releases authoring in parallel" model actually work when the same record gets touched by more than one release cohort.
| Item | Detail |
|---|---|
| Base data | Every record in a workspace tracks a "base data" value — what that record looked like in production when you started editing it there. |
| Conflict trigger | If production has since diverged from your recorded base data — someone else's change from an earlier release published in the meantime — and you've also modified that record, it's highlighted as a conflict to resolve. |
| Resolution options | Accept the production version as correct (drop your workspace edit), or assert your workspace change is better and let it overwrite on publish. |
| Worked example | A CMS-related record targeted for 2.86 gets edited in your workspace. Meanwhile 2.84/2.85 ship first and happen to touch the same record. When your 2.86 work later touches it, you get a conflict error — the base data moved out from under you. |
| Confirmed live | You keep full editing capability regardless of what's on hold or not yet in production — the conflict flag is a signal to reconcile, not a block on working. |
Demo was mid-example (term 1000-2-5, showing workspace-vs-database divergence) when this chunk of transcript ended — more detail to follow as the demo continues.
How tasks get created
Two distinct paths into a task, plus sizing and naming guidance.
| Item | Detail |
|---|---|
| Reactive fixes | A Help Scout inquiry ("these terms are wrong") becomes a standalone task — description of the needed change, targeted to a release, assigned to whoever can make it. Not tied to a formal "requested link" submission (that requirement is going away for this class of work). |
| Planned / submission-driven work | Tasks tied to requested changes and submissions already in the pipeline get set up during the pipeline planning calls. |
| Sizing | Keep tasks small and logically scoped — unless the content is genuinely one big logical unit (e.g. CMS). Example: ~50 allergy terms across 5 submissions can be one task ("allergy terms for 286"); the underlying items still belong to their individual submissions and route back there when done. |
| Mental model | A task is an abstraction layer over the underlying submissions/requests — analogized live to a Git branch. Task-within-task nesting: just one level for now. |
| Naming | Steven's strong preference: lead with an action verb, so the task name says what's being done, not just what it's about. |
Mock month calendar
Steven built a mock calendar during the break to visualize a month of the new cadence. Walkthrough was still going when this update was captured.
| Item | Detail |
|---|---|
| Calendar goes public | Decided: the release/validation/authoring calendar will be published on the LOINC all-team calendar — lets anyone check what release is happening in a given week before requesting time off. Directly supports the Day 1 capacity-planning practice. |
| Authoring isn't scheduled | Confirmed: authoring runs continuously every week and doesn't get called out on specific calendar slots — consistent with the Day 1 model where authoring spans multiple releases at once, at all times. |
| Worked hypothetical | Starting in September: 2.84 authoring runs from "now" through a cutoff of the 15th of October — matches the Day 1 concept of content freeze as a fixed date, not a window. |
Two loose ends in this segment: a reference to "a slot in the first 12 months" tied to "the project we're going to do for the releases" (meaning unclear so far), and a note that some part of this is waiting on Felicia's return before going further. Walkthrough continues — more to follow.
| Item | Detail |
|---|---|
| Planning call | 90 minutes, planning only — no retrospective folded in. Repurposes the existing Thursday slot rather than adding a new one. |
| Date | First Thursday of every month. Second Thursday (closer to the 15th cutoff) was considered and passed over in favor of consistency and leeway around the cutoff date. |
| Standups | No standup on the planning-call Thursday. Regular Tuesday/Wednesday/Thursday standups continue otherwise, indefinitely. |
Target-release decisions become a group call
Deviating from a planned release target moves from an individual call to a group decision. Steven had the whole room explicitly acknowledge this rather than nod along.
| Item | Detail |
|---|---|
| The change | Previously, individuals could effectively commit release targets on their own — e.g. in stakeholder meetings (Wednesday afternoons with Stan called out specifically). Going forward, deviating from a planned target is a group decision. |
| Explicitly not prohibited | Informing the group about individual work stays completely normal — e.g. "CMS work came in, I'll flag it at the next standup" needs no pre-approval. |
| Open question (unresolved) | Exact order of operations: can you set a target release on something to avoid losing track of it, then bring it to the group afterward — or does the group need to sign off before the target is set? Posed live, not answered in this segment. |
| Also open | How this applies to ad hoc/urgent items (e.g. an urgent request that Elizabeth picks up) — raised, cut off mid-example. |
Team members named as needing to explicitly agree to this: Jennifer, Tim, Joshua Green, Jeffrey, Isa, Elizabeth, Felicia, Marjorie, April.
Planning-call scope: cross-team priorities?
Should part of the monthly planning call cover priorities across the whole team, not just release content?
Steven raised broadening the call beyond release-specific technical planning to also cover what other priorities are happening across the team — not most of the 90 minutes, but enough to keep everyone aligned. Joe's framing: treat part of it like a priorities readout ("here's our three technical priorities, here's the big three things coming down the pipe") so the group can gauge alignment, size discussion time, and flag anything needing its own dedicated deep-dive (e.g. a major workflow change affecting everyone).
This came up because a discussion earlier in the week with Rob and Sam — which Joe had missed — covered what's needed to support other domain models, described as a "square peg, round hole" problem with the current database structure. Background context only so far; not a decision, and not yet tracked as its own topic.
Two overhaul initiatives: database rebuild vs. request model
Directly follows from the domain-model discussion above — the foundational work that would be needed to support it.
| Item | Detail |
|---|---|
| Database rebuild ("down to the studs") | Rob's proposal: a full rebuild/decoupling of the database itself, not the application code or tooling layer. |
| Submission → request model | Rework "submission" terminology/model into "requests" — a request better reflects something actually sent in by someone; also wants a clean split between genuinely new content and revised content, rather than folding new content in as "revised." |
| Sequencing | Debated, not resolved: doing the request/submission overhaul first risks revisiting it once the database rework lands. Alternative: decouple the two efforts so they run in parallel instead of one blocking the other. |
| Why the database work is hard | Substantial business logic lives directly in the database today — stored procedures, not application code — tightly coupled to specific tables and fields (Radiology and Document Ontology given as concrete examples). This coupling is a major obstacle to cleanly building out workspaces and decoupled architecture, directly relevant to today's workspace/conflict-detection demo. |
| Guiding philosophy | Steven: "the database should just be a database, not a program." Internal/business logic in the data layer needs to be decoupled and pulled out. |
| Confirmed: two parallel initiatives | (1) Decouple business logic out of the database. (2) Overhaul requests/submissions, decoupled from the terminology database. Confirmed these can run in parallel rather than needing to be serialized. |
| Capacity concern | Raised, not resolved: the team already has a lot in flight (the monthly-release transition itself). Idea floated: draw on AI budget for this kind of internal-process work, not just content work. "We just got to figure that out." |
| Where does this get tracked? | Decided: Steven will create a "strategic priorities" project in Basecamp. Explicit worry that drove it: "I don't want it to live in a parking lot and get lost forever." The two initiatives go in as tasks with check-ins for now, refined as next steps get figured out. |
Pre-work required ahead of the planning call
| Item | Detail |
|---|---|
| The requirement | Terminologists/developers evaluate their own current state ahead of the call — what they have, what packages/tasks they're likely to work on — so they arrive with priority-based thinking already done. |
| Timing & budget | Happens before the call, not during it. About one hour budgeted for the evaluation. |
| Process | Each person evaluates independently, brings their own proposal into the call, and it's checked against agreed criteria as a group — ties directly into the group-decision governance change above. |
| Task-building during pre-work | Fine to build draft tasks and group related items (e.g. bundling related submissions into one task) without targeting a release yet — targeting happens at or after the planning call. |
Also flagged: Ontology work is tracked in a separate system ("their Jira"), not LOINC's own planning tooling — so anything the team commits to that touches the ontology space needs to be explicitly surfaced, since it won't automatically show up in LOINC's own planning view. Full mechanics still maturing; the awareness requirement itself is agreed.
Mock planning-call role-play
Lunch arrived, but Steven chose to spend the remaining time actually role-playing a planning call rather than just describing one.
Framing for the real (future) planning call: team members surface what they're thinking of bringing beforehand (e.g. via the Tuesday/Wednesday touchpoints), so everyone already has a feel for what's being proposed by the time the call happens. The call itself then becomes a group confirm/adjust session — agree, disagree, remove, add — rather than a cold start. This directly reinforces the planning-call pre-work decision above.
The room then began actually walking through a live example together — cut off before the specifics landed. More to follow as the exercise continues.
Open / unresolved
| Item |
|---|
| Order of operations for target-release assignment under the new group-decision governance — set target first and inform the group after, or group sign-off first? |
| How the group-decision governance applies to ad hoc/urgent items. |
| Whether/how to fold cross-team priority alignment into the monthly planning call. |
| What supporting other domain models actually requires — background from a Rob/Sam discussion earlier in the week, may need its own follow-up. |
| How the database-rebuild and request/submission initiatives fit alongside the team's existing capacity (already stretched by the monthly-release transition) — raised, not resolved. |
| "Slot in the first 12 months" reference from the mock-month walkthrough — unclear. |
| Whether the mock-month calendar work is waiting on Felicia's return, and for what. |
Sources
Live transcript of the HDS Team F2F, Aug 28, 2026, captured via Zoom. Full discussion detail is kept in loinc-processes/ReleaseTasks/loinc-monthly-release-e2e-workflow/e2e-workflow-notes.md.